On 7/28/2015 starting at 19:00 CDT and in a window lasting 6 hours,
the UPS maintenance techs will be doing maintenance work on both UPS
systems for the	 datacenter.

UPS#2 will be having a full maintenance	work done, while UPS#1 is something
just cosmetic, and will be done	much sooner.

The systems will be in bypass during their work. We've asked specificly
that they be worked on sequentially (even if the techs were planning to).

We will be monitoring our systems for the period of the maintenance
work, but we expect no issues for this maintenance period. The people
involved in the last issue are not allowed to work on the UPSs now.

If you have any further problems or questions please let us know at
[log in to unmask], or call us up at 612-337-6340.

Thank you.
--
Doug McIntyre    <[log in to unmask]>
  -- ipHouse/Goldengate/Bitstream/ProNS --
 Network Engineer/Provisioning/Jack of all Trades